Electricity Connection Cost in Sri Lanka (CEB/LECO 2025)
December 25, 2025
Electricity Connection Cost in Sri Lanka (CEB/LECO 2025)
Powering up your build.
You need electricity from Day 1 for construction.
1. Cost Breakdown (2025)
- Single Phase (30A): Enough for a small house (no heavy A/C).
- Cost: Rs. 20,000 - 30,000.
- Three Phase (30A/60A): Required for big houses with multiple A/CS, pumps, or EV chargers.
- Cost: Rs. 50,000 - 75,000.
Note: If you need to install a new concrete pole, add ~Rs. 30,000 per pole.
2. Construction Connection
Don't use a domestic connection for building (illegal). Apply for a Temporary Construction Connection.
- Rate: Higher tariff (General Purpose).
- Process: Convert to "Domestic" once COC is obtained.
3. Net Metering (Solar)
If you plan to get Solar:
- You need a standard connection first.
- Then apply for "Net Metering" or "Net Accounting" to export excess power.
- Benefit: Zero electricity bill if sized right.
Stay safe. CEB outage app